Datacenters#

Get datacenter information

Endpoint#

GET

https://vulcan.api.synmax.com/v2/datacenters

Request Examples#

curl -X GET "https://vulcan.api.synmax.com/v2/datacenters" \
-H "Access-Key: $API_TOKEN"

Response#

Parameters

Type

Description

Example

balancing_authority

string

IIR data center unit capacity in megawatts (MW)

ERCOT

created_at

string

ISO date on which the record was created

2023-01-01T12:00:00Z

data_center_type

string

IIR type of data center

Hyperscale Data Center

date_construction_50_percent_complete

string

Date where a data center has been deemed to appear 50% complete

5/18/2025

date_construction_completed

string

Date where data center has been deemed complete based on satellite observations

6/30/2025

date_construction_start

string

Start date of construction for a given data center

2023-08-20

date_first_structures

string

Date where the first permanent structures are identified for a given data center

7/12/2023

date_image

string

Date of the latest available satellite image

2025-04-27

date_land_cleared

string

Date of first land cleared for a given data center

2023-03-19

date_planned_operation

string

IIR online date for a given data center

2026-07-31

date_updated

string

Date of each update to the dataset

2025-04-28

date_vulcan_earliest_online

string

The earliest possible date a data center is projected to be operational

2/7/2024

date_vulcan_earliest_plus_7

string

The earliest possible date a data center could be operational if construction were to start 1 week after the last update.

1/2/2026

date_vulcan_latest_online

string

The latest possible date a data center is projected to be operational

7/24/2027

date_vulcan_median_online

string

The median date a data center is projected to be operational

5/15/2026

date_vulcan_status_change

string

Date of which the data center status was changed to under construction

5/29/2025

iir_minus_vulcan_earliest_online

integer

The difference in days between the IIR startup date and the Vulcan earliest date

139

iir_minus_vulcan_latest_online

integer

The difference in days between the IIR startup date and the Vulcan latest date

-1124

latitude

number

EIA plant latitude

33.0225

longitude

number

EIA plant longitude

-102.709

observation

string

Observations or relevant data center comments after reviewing satellite images

land cleared

owner_name

string

IIR owner of data center

CloudHQ LLC

plant_id

integer

IIR plant id

68847

plant_name

string

IIR plant name

1000 Mile Solar

plant_status

string

IIR construction status of the data center

[‘Under Construction’]

source

string

The source of data center data

EIA

state_code

string

2 letter state code - provided by IIR

TX

synmax_id

string

A unique key of plant id and unit id

68847-PV1

unit_capacity

number

IIR data center unit capacity in megawatts (MW)

108

unit_id

integer

IIR id given to each unit for a given data center

2548109

unit_name

string

IIR name of each unit for a given data center

LC11DC1

unit_status

string

IIR construction status of the unit for a given data center

Engineered

vulcan_status

string

Indicates if a data center has been observed to be under construction

Confirmed

Normal Output#

plant_id

plant_name

unit_id

unit_name

owner_name

state_code

balancing_authority

unit_capacity

unit_status

plant_status

date_planned_operation

data_center_type

date_vulcan_status_change

date_image

vulcan_status

observation

date_construction_start

date_land_cleared

date_first_structures

date_construction_50_percent_complete

date_construction_completed

date_vulcan_earliest_plus_7

date_vulcan_earliest_online

date_vulcan_latest_online

days_iir_minus_vulcan_earliest_online

days_iir_minus_vulcan_latest_online

synmax_id

source

created_at

modified_at

3492281

Abilene - Longhorn Data Center Campus (Stargate)

2546924

CADCP4

Abilene - Longhorn Data Center Campus (Stargate)

Texas

ERCOT

200.00

Engineered

Under Construction

2026-07-31

Data Centers

2025-04-23

2025-05-11

Confirmed

land cleared

2025-01-31

2025-01-31

TBD

TBD

TBD

2026-01-20

2028-04-04

TBD

TBD

3492281-2546924

IIR

TBD

2025-05-12

3492281

Abilene - Longhorn Data Center Campus (Stargate)

2546952

CADCP5

Abilene - Longhorn Data Center Campus (Stargate)

Texas

ERCOT

200.00

Planned

Under Construction

2027-05-31

Data Centers

2025-05-11

none

TBD

TBD

TBD

TBD

TBD

3492281-2546952

IIR

TBD

2025-05-12

3492281

Abilene - Longhorn Data Center Campus (Stargate)

2546953

CADCP6

Abilene - Longhorn Data Center Campus (Stargate)

Texas

ERCOT

200.00

Planned

Under Construction

2027-08-31

Data Centers

2025-05-11

none

TBD

TBD

TBD

TBD

TBD

3492281-2546953

IIR

TBD

2025-05-12

3492281

Abilene - Longhorn Data Center Campus (Stargate)

2587917

CADCP7

Abilene - Longhorn Data Center Campus (Stargate)

Texas

ERCOT

200.00

Planned

Under Construction

2027-12-29

Data Centers

2025-05-11

none

TBD

TBD

TBD

TBD

TBD

3492281-2587917

IIR

TBD

2025-05-12

3492281

Abilene - Longhorn Data Center Campus (Stargate)

2546912

CADCP2

Crusoe Energy Systems, Inc

Texas

ERCOT

200.00

Under Construction

Under Construction

2026-02-27

Data Centers

2025-05-11

none

TBD

TBD

TBD

TBD

TBD

3492281-2546912

IIR

TBD

2025-05-12

3492281

Abilene - Longhorn Data Center Campus (Stargate)

2546930

CADCP3

Crusoe Energy Systems, Inc

Texas

ERCOT

200.00

Under Construction

Under Construction

2026-06-30

Data Centers

2025-05-11

none

TBD

TBD

TBD

TBD

TBD

3492281-2546930

IIR

TBD

2025-05-12

3589794

Adair Data Center Campus

2547786

AADCB1

Adair Data Center Campus

Iowa

MISO

100.00

Planned

Planned

2026-12-31

Hyperscale Data Center

2025-05-11

none

TBD

TBD

TBD

TBD

TBD

3589794-2547786

IIR

TBD

2025-05-12

3589794

Adair Data Center Campus

2547787

AADCB2

Adair Data Center Campus

Iowa

MISO

100.00

Planned

Planned

2027-12-31

Hyperscale Data Center

2025-05-11

none

TBD

TBD

TBD

TBD

TBD

3589794-2547787

IIR

TBD

2025-05-12

3629131

Adairsville Data Center Campus (Project Springbank)

2593495

Adairsville DC01

Atlas Development LLC

Georgia

70.00

Planned

Planned

2027-03-31

Hyperscale Data Center

2025-04-18

none

TBD

TBD

TBD

TBD

TBD

3629131-2593495

IIR

TBD

2025-05-12

3526188

Aldie Arcola Data Center

2547793

Arcola DC2 2N

Yondr USA LLC

Virginia

PJM

48.00

Under Construction

Operational

2025-06-30

Data Centers

2025-05-12

2025-05-12

Confirmed

structures visible

2024-12-30

2024-06-17

2024-12-30

TBD

TBD

TBD

2025-10-13

2027-04-08

TBD

TBD

3526188-2547793

IIR

TBD

2025-05-12